Time-Line
Date |
Activity |
Status |
Mai-June |
Frankfurt electricians to visit MPI and inspect White + Blue containers |
Done |
End June |
DWD Wind-Mast removed to make room for gas bottles and blue container |
Done |
11.07 |
Start of road construction on L3024 |
started |
19th Juli |
Gas-Bottles delivered (Buendle, Palleten)* |
Done |
Juli |
Dead tree removed |
Done |
20/21st July |
Platform constructed on roof |
Done |
25.07 |
Hired-Container from RMB delivered |
Done |
28.07 |
DOAS set up (Roof and Upper-container) |
in progress |
28.07 |
Blue Container from MPI transported to KF |
Done |
28.07 |
White Container from MPI transported to KF |
Done |
01.08 |
IT improvements at Observatorium |
Done |
02.08 |
Containers connected to power |
Done |
05.08 |
Liq-N2 Delivery (600 L Tank) |
Done |
08.08 |
Start of set-up phase |
|
15.08 |
Start of measurement phase |
|
21.08 |
End of Road construction on L3024 (hopefully) |
|
09.09 |
End of campaign |
Instrument Arrivals at Kleiner Feldberg
Group |
Arrival at KF |
MPI-Wagner |
01-05 August |
MPI-Williams |
3rd August |
Wuppertal |
3-4 Aug (sprinter arriving at noon on 3rd) |
MPI-Drewnick |
3rd-5th August |
Bremen |
7th August, Sunday afternoon, evening |
Jülich (LOPAP) |
8th August |
Jülich (J) |
12-13th August |
Uni-Mainz (Heiko) |
2-5th August |
MPI-Harder |
Ab 08 August |
MPI-Crowley |
04-07 August |