KF 2011 Things to do:

Time-Line

Date

Activity

Status

Mai-June

Frankfurt electricians to visit MPI and inspect White + Blue containers

Done

End June

DWD Wind-Mast removed to make room for gas bottles and blue container

Done

11.07

Start of road construction on L3024

started

19th Juli

Gas-Bottles delivered (Buendle, Palleten)*

Done

Juli

Dead tree removed

Done

20/21st July

Platform constructed on roof

Done

25.07

Hired-Container from RMB delivered

Done

28.07

DOAS set up (Roof and Upper-container)

in progress

28.07

Blue Container from MPI transported to KF

Done

28.07

White Container from MPI transported to KF

Done

01.08

IT improvements at Observatorium

Done

02.08

Containers connected to power

Done

05.08

Liq-N2 Delivery (600 L Tank)

Done

08.08

Start of set-up phase

 

15.08

Start of measurement phase

 

21.08

End of Road construction on L3024 (hopefully)

 

09.09

End of campaign

 

Instrument Arrivals at Kleiner Feldberg

Group

Arrival at KF

   

MPI-Wagner

01-05 August

MPI-Williams

3rd August

Wuppertal

3-4 Aug (sprinter arriving at noon on 3rd)

MPI-Drewnick

3rd-5th August

Bremen

7th August, Sunday afternoon, evening

Jülich (LOPAP)

8th August

Jülich (J)

12-13th August

Uni-Mainz (Heiko)

2-5th August

MPI-Harder

Ab 08 August

MPI-Crowley

04-07 August

   
   

 